These are a must have tool for anyone that works alone and they make a 2 man crew more productive when laying out a parking lot.If you just need it for chalking a line on driveways, you could use a one piece handle ( seen on left) it wont hold the extras but it is very handy. Your chalk line ring will slide over & down the handle so the string goes under the weight with little effort.
Most of us have enough scrap around to build one or two. It took me about
3 hours to build two of them.
Weight...2" x 16" solid shaft (anything that sits flat,is 6"x6" & 14-15 lb will do)
Rail...3/8" or 1/2" x 27" steel rod or rebar
Handle... 5/8 or 3/4" x 12" rod or rebar
Tape holder...1/4" x 3" rod or bolt
Crayon holder...1" pipe x 3"
Wood dowel...3/4 x 28" (painted red)
Rubber hose ...3/4 I D x 6"
Put three 45 deg bends in the handle as shown. & weld to rail.
Put 45 deg bend on tape holder about 2" out. & weld to rail 16" up from bottom.
Cut 1" x 3" pipe to 2" & 1" pcs. weld 1'' pc to back of handle. Weld 2" pc to weight.
Weld your weights together (if needed)
Weld handle/rail assy to weight & paint. I drilled & taped the first one, that took to long & was hard to get stright without a drill press.
I used elect tape for the stripe. Use 6" hose to hold crayon to dowel.
18 lbs total.
Most of us have enough scrap around to build one or two. It took me about
3 hours to build two of them.
Weight...2" x 16" solid shaft (anything that sits flat,is 6"x6" & 14-15 lb will do)
Rail...3/8" or 1/2" x 27" steel rod or rebar
Handle... 5/8 or 3/4" x 12" rod or rebar
Tape holder...1/4" x 3" rod or bolt
Crayon holder...1" pipe x 3"
Wood dowel...3/4 x 28" (painted red)
Rubber hose ...3/4 I D x 6"
Put three 45 deg bends in the handle as shown. & weld to rail.
Put 45 deg bend on tape holder about 2" out. & weld to rail 16" up from bottom.
Cut 1" x 3" pipe to 2" & 1" pcs. weld 1'' pc to back of handle. Weld 2" pc to weight.
Weld your weights together (if needed)
Weld handle/rail assy to weight & paint. I drilled & taped the first one, that took to long & was hard to get stright without a drill press.
I used elect tape for the stripe. Use 6" hose to hold crayon to dowel.