PDA

View Full Version : Production on pavers, in square feet


cleancutccl
06-22-2009, 12:14 PM
Just wondering what some other companies paver production is per day 10 hour day. I'm just talking screeding sand and laying pavers, then if you know how many tons of base per day that would be a good comparison too. Thanks,

Garrett

Sunscaper
06-22-2009, 05:07 PM
600-800 square feet per man

philboudreault
06-22-2009, 08:27 PM
no job is really the same old house ... new houses .....different stones....design and cuts all make a huge difference....but for a plain jane come in and install u should go with sunscaper's 600-800 feet .....but then a gain ...so many factors

cleancutccl
06-24-2009, 12:20 AM
sunscaper, how many man crew are you talking?

Sunscaper
06-24-2009, 10:29 AM
I run anywhere from 3-10 depending on the job. As philboudreault stated though this is a rough estimate on a straight run i.e. parking lots, or large driveways. Cuts are the death of productivity. Hope this helps you.