03-16-2012, 07:27 PM
ok i need some help grouping jobs on the mobile. lets say you did 3 lawn cuttings in a row. and you get out and hit the start time.After you finis all 3 you hit the stop. how can you distribute the times over the 3. just like if you are on the desk top. you hight light the 3 jobs you want to record then click distribute and it sends the recorded time over the 3 jobs based on man hours. or is there a better way?????

Help Help Qxpress users...
Ps I called support today and they didn't have a clue. and they didn't even know you can do it on the desk top.

thanks so much

grass-scapes
03-17-2012, 10:41 PM
Set up each job individually, and click the start and stop on each. That seems to be the simplest solution. Why would you evenly distribute the time, when one may take much longer than the others. It will give you a better look at your job costing if you do it by each job.