I am meeting with a home builder this Monday and he wants to discuss grading and levelling for a new home division in my area. I haven't worked doing grading on new homes and was wondering the steps to accomplish this. If anybody had the time to explain it to me it would be muchly appreciated. From excavation of basement to rough grade and final grade. I have about 1000 hours on my machine and feel very confident but am just unsure as to what they might expect. Thanks.
What they will expect is variable but here this is what a builder would expect. Excavate basement (usually 9' walls with 10' footings), dig in utilities, here some want water and sewer hooked up others will have a plumber do the connections. Backfill/rough grade foundation and final grade the home. Equipment used here, backhoe or preferably exxcavator and or loader/SSL/CTL type machine.
__________________
See us at www.kaiserskidsteer.com

Proudly running CASE and Takeuchi equipment.
Reply With Quote
 
Page generated in 0.03808 seconds with 7 queries