Thanks and keep them coming
That $2500 figure was not total. That was the cost of materials, the killing of the existing turf, and roughly 2 to 3 days labor for my guys. Trucking is included in the price of the stone, they said maybe an additional $100. They are located less than a mile from where the job site is which makes it great in that respect.
I figure maybe exact cost of materials with 15% markup, plus labor and other expenses and maybe what I would like to make for a couple days work.
I came up with roughly $3850 total. Does that seem ok?
|