Bid Question

Wanted to Know if this bid sounds close to accurate.

7500 Sq Ft. 4" Top soil to be added to rough grade lot. $1800
6900 Sq Ft. Sod to be put in $1850
600 Sq Ft. Mulch to be put in $70
Skid steer 3.5 days Total: $700
Power Rake 1 day: $200
Trencher 1 day: $200
Sprinkler System Installed: $1350

Total of: $6150.00

Does this number sound good for materials and equipment?

My Partner and I will be working on this for an estimated 5 days. Any opinions for labor rates?

Thanks

jrussell