patio example

600 sf @ $24 = $14,400
additional fill 30 tons stone dust @ $50 = $1,500
walls for raised patio 100 lf @ $52.50 = $5,250
debris disposal 12 tons @ $50 = $600

Total $21,750

Two weeks 4 man crew 320 man hours @ $20 loaded cost = $6400
Material (most expensive = flag stone) 720 sf @ $3.75 = $2700
Wall material (natural stone) 11 tons @ $100 = $1100
Truck and skid steer loaded cost 2 weeks @ $500 = $1000

Total direct cost = $11,200

Our normal crew tool list is sufficient...worm drive 7" saws w/ diamond blades, gas 14" cutoff saw, 4000# plate compactor, hand tools. No lasers, we still use rebar, string, and string level, they are great for us.