Charging more than proposal/estimate

I was wondering what you guys do when a job takes longer than expected with the final invoice/bill due to taking longer than expected?

I give them an estimate and describe the steps involved but I haven't been doing very well at estimating the hours involve since I haven't had any experienced people working for me this year. Do you guys eat the cost of the extra labor or do you still charge for all the hours worked? I will charge extra for legit reason like finding an old foundation or extra crappy dirt we have to haul out and bring in better.

I have a disclaimer on the estimate saying just that, This is an estimate and can change depending on total hours involved in the project and quantity of materials used since there can be unexpected things in the ground or something built not like it should have been and so on. I have been eating the cost mostly unless it was something they changed and get charged accordingly. I look at it as if I were them, in the fact that its not their fault that the employees worked slow so why should they have to pay for it.

All these unexperienced employees have cost me $10,000-20,000 in hours I haven't been able to bill since we were not as efficient as I had pictured in my mind when I did the estimate during the winter. Some of it is my fault for not estimating higher but I didn't think I wouldn't be able to find at least one person who could work hard. I have hired 6 so far this year and down to maybe one but doesn't seem like he will work out either. The longest one lasted 3 months.
Reply With Quote
  #2  
Old 09-04-2013, 01:58 PM
Stillwater Stillwater is offline
LawnSite Platinum Member
 
Join Date: Mar 2006
Location: The United States
Posts: 4,250
It depends on the specific reasons for the overage, it would be better to correct the causes by working on your reasons for inefficiency. Before your credibility is questioned.
Reply With Quote
  #3  
Old 09-04-2013, 03:59 PM
jsslawncare's Avatar
jsslawncare jsslawncare is offline
LawnSite Bronze Member
 
Join Date: Feb 2011
Location: North Georgia
Posts: 1,672
Charging more than proposal/estimate

I have read this post and that's all I can say...
__________________
All equipment is wore out. <- Never mind. All equipment has been repainted and with new decals. It's like I have new mower's again!
48" Ferris WB
36" Ferris WB
All Echo hand helds
<- That's how I feel at the end of the day.
Reply With Quote
  #4  
Old 09-04-2013, 04:23 PM
GrassGuerilla GrassGuerilla is offline
LawnSite Bronze Member
 
Join Date: Aug 2008
Location: St. Louis Missouri
Posts: 1,420
Sounds like you screwed the pooch. You covered your butt with the "extras" clause. But from your description, it sounds like you bid a job you don't have the labor force to do. Did you encounter issues that added to your estimate, or did you simply underestimate?

My bid is my bid. It doesn't change unless the job does.
Reply With Quote
  #5  
Old 09-04-2013, 09:16 PM
DVS Hardscaper's Avatar
DVS Hardscaper DVS Hardscaper is offline
LawnSite Fanatic
 
Join Date: Aug 2005
Location: County Jail
Posts: 5,867
You can not charge a customer for your incompetence. You estimated the job, you should know what you're doing.

There is an exception for when I may charge for additional materials. If I have time later tonight ill go into detail.

Last edited by DVS Hardscaper; 09-04-2013 at 09:20 PM.
Reply With Quote
  #6  
Old 09-04-2013, 09:35 PM
Red Shed Landscaping Red Shed Landscaping is offline
LawnSite Member
 
Join Date: Mar 2007
Location: North Central IA
Posts: 175
Like I said I haven't been charging for the overages due to me underestimating or the guys not performing to my ideals.

I have been estimating the projects based on what I have done in the past and how I work but not taking into consideration for how my employees have been working which is slow and can't comprehend the littlest things like how to dig a trench.

I was pretty sure most to all of you would be on the same page that you can't charge more for no additional surprises or changes. I have always been that way but it has been way worse this year since I have been training so many people. I can just chalk it up to opportunity/building business cost.
Reply With Quote
  #7  
Old 09-04-2013, 09:49 PM
GOATMAN GEORGE GOATMAN GEORGE is offline
LawnSite Member
 
Join Date: Jun 2013
Location: North Carolina
Posts: 88
Quote:
Originally Posted by DVS Hardscaper View Post
You can not charge a customer for your incompetence. You estimated the job, you should know what you're doing.

There is an exception for when I may charge for additional materials. If I have time later tonight ill go into detail.
Seriously +1. Your going to get horrible reputation if you decide to charge your underestimated labor. You lost that $10'000 to 20000 yourself by bad estimating. The simple solution is estimate better.
Reply With Quote
  #8  
Old 09-04-2013, 10:35 PM
tthomass's Avatar
tthomass tthomass is offline
LawnSite Gold Member
 
Join Date: Jun 2006
Location: N. VA
Posts: 3,442
It may be best to sub contract larger jobs, or jobs that are more technical and learn from them. Then as you grow, hire on the right people to build your projects. Make sure you use an A+ contractor though.
Reply With Quote
  #9  
Old 09-04-2013, 10:36 PM
MJK MJK is offline
LawnSite Senior Member
 
Join Date: Jun 2006
Location: Michigan
Posts: 356
It's a very bitter pill to swallow, but that's all you can do, change your production times. For me, we used to have problems with workers, invest in equipment or rent and limit the amount of bodies needed on a job site as possible. We only need 2 good hands plus my self to do every job profitably.
Reply With Quote
  #10  
Old 09-05-2013, 06:26 PM
promower's Avatar
promower promower is offline
LawnSite Bronze Member
 
Join Date: Jan 2003
Location: Wisconsin
Posts: 1,221
How much are you paying your workers? You get what you pay for, I would look I to skilled workers with references
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump






Powered by vBulletin® Version 3.8.6
Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Copyright ©1998 - 2012, LawnSite.comô - Moose River Media
All times are GMT -4. The time now is 06:56 AM.

Page generated in 0.11597 seconds with 7 queries