Proper sidewalk construction
A local construction company is replacing the sidewalks from our new road construction. What is the proper way to prep and pour. It seems like they are putting down about 2" of gravel, tamping and then pouring. Is that all that is needed? They will be doing our side of the street starting soon. The other side looks uneven and just plain bad.
Thanks VO
__________________
"I just noticed the light at the end of the tunnel burned out" |
|
#2
|
||||
|
||||
|
have to have expansion joints
|
|
#3
|
||||
|
||||
|
That's about right for prep on a concrete sidewalk. The surprise is that they tamped it. Most guys I know just use 2"-4" of pea gravel and just pour on top after raked out.
The real question is how strong is the concrete they are using. If they are using fiber reinforcement, then the thing should stay true and strong. Mt. Pleasant Eh? I grew up across the river in IL. Dated a girl from Mt. Pleasant for a while back in the day. ...
__________________
White Gardens On Facebook.......WG Thread......Greencare For Troops......... mywhitegardens.com(under construction) 2005- Completion of University of Illinois Master Gardner's Program. |
|
#4
|
|||
|
|||
|
1/2 in rebar 4000 lb per sq inch and expansion joints. Usually they at least do a cut/edge every 4ft w expansion every 12. But more the better
Posted via Mobile Device |
|
#5
|
||||
|
||||
|
Maybe some Steel Wire Remesh
|
|
#6
|
||||
|
||||
|
12' is way over kill. More is better huh? How often do you want it? Every 4'? LOL
__________________
![]() Quote:
|
|
#7
|
|||
|
|||
|
LOL. I know how that can be interpreted. I meant typically i put it in every 3 4 foot sections. The more expansion joints in his sidewalk construction the better to eliminate cracking and freeze thaw problems. I am from NY. So We get a lot of freezing.
|
![]() |