Dirt Production Rates

Hi guys,

I'm bidding some soil prep and wanted some feedback on production.

Does 30-40 cubic yards per hour to spread piled topsoil to finish grade sound like normal production rate?

Pile size = 12 cubic yards from tandem dumps layed out where I want. (close)

Area = wide open 130,000 sq.ft.

Machine = CAT Multi-Terrain Loader 85 hp with 6ft wide tooth bucket

Conditions = dry/normal

Sub-grade = +/- 1" before I start

Thanks

Matt
Reply With Quote
  #2  
Old 02-11-2012, 03:30 PM
muddywater muddywater is offline
LawnSite Bronze Member
 
Join Date: Sep 2011
Posts: 1,813
Can you get 30-40 yards delivered every hour?
Reply With Quote
  #3  
Old 02-11-2012, 08:05 PM
Landrus2's Avatar
Landrus2 Landrus2 is offline
LawnSite Platinum Member
 
Join Date: Dec 2006
Location: Big apple
Posts: 4,694
That all is going to depend on the operator have you looked into a Harley rake
Reply With Quote
  #4  
Old 02-14-2012, 12:31 AM
Gr8WhiteNorth Gr8WhiteNorth is offline
LawnSite Senior Member
 
Join Date: Oct 2007
Location: Manitoba, canada
Posts: 370
Yes, dirt can be hauled at that rate. Supply is within 1/4 mile and trucking co has tons of tandems so it shouldn't be a problem.

I've seen videos on the harley rakes but never used one. Dragging weighted harrows and steel drag seems faster because I can get 12 feet wide. I haven't compared directly but open to the idea if you think it would work better.

I could see the Harley rake working great on hard packed soil. The drags are quick on fresh stuff.
Reply With Quote
  #5  
Old 02-14-2012, 12:51 PM
Executive Landscape Executive Landscape is offline
LawnSite Member
 
Join Date: Jan 2012
Location: Michigan
Posts: 17
Finish grade or rough grade? seed or sod? irrigation to work around or no? Harley rake would work well if its a finish grade but you will need to drag out with the bucket first unless the delivery trucks can spread it out for you reasonably well. If you are really good in that cat you might be able to get it done without additional equipment and yes 30-40 yards per hour is doable IF you are really good in your cat and the delivery trucks can drag it out a bit for you so your not dealing with 5' tall piles.. A very good dozer operator might work fastest.
Reply With Quote
  #6  
Old 02-14-2012, 11:40 PM
Gr8WhiteNorth Gr8WhiteNorth is offline
LawnSite Senior Member
 
Join Date: Oct 2007
Location: Manitoba, canada
Posts: 370
Area is to be seeded. Finished quality doesn't need to be as perfect as sod. No irrigation.
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump






Powered by vBulletin® Version 3.8.6
Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Copyright ©1998 - 2012, LawnSite.comô - Moose River Media
All times are GMT -4. The time now is 08:19 PM.

Page generated in 0.07859 seconds with 7 queries