Production Times - Pavers

This ought to be interesting.....

Ok, let's say you have an ideal scenario. It's a driveway and so access is really easy. No lugging pavers all the way around the house. And let's assume you can have the pallets of pavers delivered pretty close to where they will be installed. Let's also assume that it's already excavated and your fabric and lifts of compact gravel are already in place. All your crew has to do at this point is install screeding sand, screed the sand, and lay the pavers. Let's also disregard cutting too. Just getting the pavers laid out as close to the edges as possible and save the cutting for later.

The pattern your team is installing is this pattern:



So just doing the screeding sand and placement of pavers, that's all. And it's a LONG driveway. How many sq. ft. would you expect your team of 3 guys do lay down per day?
__________________
Jim Lewis
Lewis Landscape Services - Oregon
"kickin' grass and takin' names"


www.lewislandscape.com - Portland Oregon Landscaping Company

landscape design Portland Oregon
Reply With Quote
  #2  
Old 02-21-2013, 10:14 PM
DVS Hardscaper's Avatar
DVS Hardscaper DVS Hardscaper is online now
LawnSite Fanatic
 
Join Date: Aug 2005
Location: County Jail
Posts: 5,708
6 pallets per day

This is how I calculate my jobs when I get to the actual paver installation - how many pallets can we do in a day.

For a patio the guys screed and lay 5 pallets per day.

Walks are more tideous, and we usually can not get 5 pallets screeded and layed.

Driveways - at least 6. Cost will be based on 6, but that doesnt mean we won't do more.

I dont base it on SF per day, as I'm not going to stand there and measure and calculate. It's easier for me to simply count how many empty pallets are stacked on the ground.


.
__________________
"It's You vs. You"

"People Throw Rocks At Things That Shine"


My Equipment Brag List:

-1 CAT hat
-16 pairs of Hanes socks (the Heavy Duty model), many with holes.
-12 pairs of underwear, ranging from Joe Boxers to Jockey, many are in need of replacement. (no more photo requests please)
-hundreds of t-shirts. Some w/ grease stains, some torn & tattered.
-7 pairs of jeans, ranging from Levis to Polo to GAP. 1/2 of them have holes in 'em.
-1 belt
-1 pair of old worn out Nike shoes.

Last edited by DVS Hardscaper; 02-21-2013 at 10:18 PM.
Reply With Quote
  #3  
Old 02-21-2013, 10:14 PM
alldayrj's Avatar
alldayrj alldayrj is online now
LawnSite Silver Member
 
Join Date: Apr 2012
Location: Long island, NY
Posts: 2,808
If its long and not necessarily wide (like 10') we could really move, stage pallets along the side with the skid steer.drive up the base and sprinkle the sand or load barrels. Two guys feeding and staging, 1 laying, i don't see why you couldnt do 600sf in a 8 hr day. Maybe even 800. That pattern should move pretty quick. Not as fast as a 1 size paver but much faster than the new random designs
Posted via Mobile Device
Reply With Quote
  #4  
Old 02-21-2013, 10:21 PM
DVS Hardscaper's Avatar
DVS Hardscaper DVS Hardscaper is online now
LawnSite Fanatic
 
Join Date: Aug 2005
Location: County Jail
Posts: 5,708
modular patterns usually take a little longer. nope, not rocket science, but one must actually be cogisent not to let the joint lines git to long. and make shore a pattern isnt developedd.

PAtterns like the "I" Pattern, herring bone, etceterra, go faster because once it's started theirs really only one way it can go


.
__________________
"It's You vs. You"

"People Throw Rocks At Things That Shine"


My Equipment Brag List:

-1 CAT hat
-16 pairs of Hanes socks (the Heavy Duty model), many with holes.
-12 pairs of underwear, ranging from Joe Boxers to Jockey, many are in need of replacement. (no more photo requests please)
-hundreds of t-shirts. Some w/ grease stains, some torn & tattered.
-7 pairs of jeans, ranging from Levis to Polo to GAP. 1/2 of them have holes in 'em.
-1 belt
-1 pair of old worn out Nike shoes.
Reply With Quote
  #5  
Old 02-21-2013, 10:27 PM
MJK MJK is offline
LawnSite Senior Member
 
Join Date: Jun 2006
Location: Michigan
Posts: 354
650-700 sq ft the first day. That pattern lays pretty quick, so I would think as the day moves along you will lay them faster and even faster the 2nd day. This is also assuming skid access.
Reply With Quote
  #6  
Old 02-22-2013, 12:16 AM
scagrider22 scagrider22 is offline
LawnSite Bronze Member
 
Join Date: Nov 2009
Location: somewhere
Posts: 1,154
Not sure, Ive never laid that pattern but I would say at least 800 sq' a day, we did an Avante Ashlar patio last summer and did 1400 sq' in one day with 3 guys but it was a large paver with a random pattern.
__________________
grk82
Reply With Quote
  #7  
Old 02-22-2013, 08:29 PM
jbailey52's Avatar
jbailey52 jbailey52 is offline
LawnSite Bronze Member
 
Join Date: Dec 2004
Location: Horticulture
Posts: 1,052
We can do 6.021 pallets.
Reply With Quote
  #8  
Old 02-23-2013, 10:13 AM
big daddy b's Avatar
big daddy b big daddy b is offline
LawnSite Member
 
Join Date: Dec 2010
Location: East Syracuse, NY
Posts: 95
With a 4-man crew, skid steer and our paver cart we normally do 1200-1500 square feet per day, that's roughly 10-12 pallets depending on square footage of each pallet. The best we ever did was 14 pallets in one day, those were 4x8s, we were screeding over concrete and it was a long day. If we dropped a crew member, we would probably be right at about 800-1,000 square feet a day, 6-8 pallets a day. Once we get moving, we usually have three guys laying and one guy moving pavers with the cart.
__________________
www.nelliganco.com
Reply With Quote
  #9  
Old 02-23-2013, 12:26 PM
zedosix's Avatar
zedosix zedosix is offline
LawnSite Silver Member
 
Join Date: Feb 2003
Location: Eastern Ontario
Posts: 2,394
hmm, with 2 men we've done 1600 with screeding and no cutting in two days. I think alot depends on conditions like temperature and if any of them had a few too many the night before.
Reply With Quote
  #10  
Old 02-24-2013, 12:52 PM
big daddy b's Avatar
big daddy b big daddy b is offline
LawnSite Member
 
Join Date: Dec 2010
Location: East Syracuse, NY
Posts: 95
Quote:
Originally Posted by zedosix View Post
hmm, with 2 men we've done 1600 with screeding and no cutting in two days. I think alot depends on conditions like temperature and if any of them had a few too many the night before.
Whaaaaaaaaaaaaaaat....I call bullshit on this. 2 Guys installed 1600 with screeding in one day? How long of a day are we talking? 12 hours...16 hours? That doesn't sound like a 8 hour day to me.
__________________
www.nelliganco.com
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump






Powered by vBulletin® Version 3.8.6
Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Copyright ©1998 - 2012, LawnSite.comô - Moose River Media
All times are GMT -4. The time now is 04:49 AM.

Page generated in 0.09008 seconds with 9 queries