Add Ons and Change orders

I have been in the landscape business 6 years now and still find it difficult to inform clients they will be billed or charged for changes to their landscape above and beyond the contract. I have a clause in my contract about change orders, but sometimes find it hard to fill out a change order when we are installing and they come out and make changes. This means I have to stop work, fill out the paper work, figure out cost, go over it with them, wait for there decision and then move on. In most cases I just make the changes and find myself getting into trouble when it comes time for final payment. Does anybody else have this problem...and if so, how do you handle it?
For example: I had a recent client who we installed outdoor low voltage lighting for. He wanted to controller out in the yard v.s. next to the outlet on the deck. So we hard wired an outlet out into his yard off his fuse panel. When I tried billing him for the labor and materials for the outlet, he thought it should be included with the lighting per the original contract. Which of course was not specific enough to state where the controller whould be plugged in.
Thanks
Reply With Quote
  #2  
Old 12-02-2003, 11:00 PM
tiedeman's Avatar
tiedeman tiedeman is offline
LawnSite Fanatic
 
Join Date: Jan 2003
Location: earth
Posts: 8,753
I would just tell him in the situation like that then that the controller will be moved to where the original plan for it was at.

I think that it a lot of times involved certain cutomers what to expect from them. You just have to feel them out. I usually just tell them ahead of time right then and there that the cost is going to be more (without the paperwork). Other customers I just go ahead and bill them for the extra work and they are fine with it. It just depends on the customers and the price involved I feel.
__________________
I use Gopher Billing & Scheduling Software
Download your FREE fully functional 30-day trial here.
Reply With Quote
  #3  
Old 12-04-2003, 12:20 AM
IRRITECH's Avatar
IRRITECH IRRITECH is offline
LawnSite Senior Member
 
Join Date: Dec 2003
Location: ATLANTA, GA
Posts: 931
Been burned a couple of times like that. Now all our contracts state that any change from the original contract will be billed seperately. i.e. unexpected rocks, etc. we also do alot of irrigation and those contracts state that the power is to be supplied by the homeowner. Just a thought
__________________
The reigning Mayor of Stupidville
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump





Powered by vBulletin® Version 3.8.6
Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Copyright ©1998 - 2012, LawnSite.comô - Moose River Media
All times are GMT -4. The time now is 12:40 PM.

Page generated in 0.07770 seconds with 9 queries