    Well, ive been working on this pretty big landscape install job for the past 4 weeks with my crew. the first 2 weeks i had between 5-8 guys working and the 3rd and 4th i had 2.

    anyway, we had to clear everything out first, there was ALOT. then dig a trench to put allan block in, we put about 350feet of alan block. there is a total of 1500 alan blocks in place now.

    we also put in stairs from the patio to the lawn, the stairs are going to look amazing once the patio blocks get put in.

    and right now were working on the patio, which is 1900sq feet. were reusing the same bricks, just washing them up and re tamping everything and making it level because its all jagged now.

    then were going to plan the flowers and install the mulch. but im getting Matt from Ground Cover Solutions to lay the mulch because its cheaper for me to contract it out then to do it myself.

    then we should be done. about 5 weeks to do it. took a little longer than expected, but then again if we would have had the right tools to begin with it would have taken about 2 weeks.

    here are some pics.

    this is a pic of the alan block around the back perimeter
     
  2. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    another shot of the alan block
     
  3. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    i sooooooo wish i would have taken before pics, it was one really bad image. heres a shot of the curve..
     
  4. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    alan block up by the house
     
  5. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    alan block around the pool.... you can see the steps getting dry fit to make sure they are going to be in level
     
  6. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    more around the pool
     
  7. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    more alan block getting in around pool
     
  8. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    steps getting dryfit and ready to be put in....



    but the steps got done today ill take a few more pic's tommarow
     
  9. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    steps again being put in
     
  10. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    straight away along the back fence with alan block
     