How long to lay sod?????

Discussion in 'Landscape Architecture and Design' started by horseman201, Dec 19, 2005.

  1. horseman201

    horseman201 LawnSite Member
    Posts: 153

    I have around 11,000 square feet of sod to lay and wanted to know how long it will take. There is not much to go around besides about 9 large oak trees. The rest is open. I have put down very small areas of sod but not this much. Prep work is already done. I tried to search this topic but could not get the search to go through. Any help would be great.
     
  2. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    I'd guess around 5 or 6 hours to lay it with 2 people, maybe less. Then use your stick edger to trim the edges.
     
  3. Lawnworks

    Lawnworks LawnSite Fanatic
    from usa
    Posts: 5,407

    That looks like 22 pallets, so I think it would be alot more than 10-12 man hours. My guess would be 25-30 man hours @ whatever you need to make per man hour.
     
  4. The Cowboy

    The Cowboy LawnSite Senior Member
    Posts: 617

    With a job like this i'd use about 2 helpers, itll probably be aroung 15-18 manhours. A good 6 hours 'll probably do the trick for the crew. I don't know how you bid it, but when I do it I charge about 4-5 bucks per roll installed for that much. It'll make me about 3500 bucks profit, give or take, thats alot better'n doing it per hour.
     
  5. AGLA

    AGLA LawnSite Bronze Member
    Posts: 1,749

    I don't think that it is realistic to expect someone who has not done big sos jobs to lay 11,000 SF of so in one day with two helpers. Plan on at least a day and a half.
     
  6. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    I dont see how it'd take 8hours or more. With 2 people, and the pallets in the right place, you can eaisly do 2000feet per hour
     
  7. Lawnworks

    Lawnworks LawnSite Fanatic
    from usa
    Posts: 5,407

    $3500 profit w/ no prep work??? I was thinking about $1500 labor at the most
     
  8. Lawnworks

    Lawnworks LawnSite Fanatic
    from usa
    Posts: 5,407

    That would be great, but I would bid for at least 24 man hours.
     
  9. RedWingsDet

    RedWingsDet LawnSite Gold Member
    from Detroit
    Posts: 3,556

    I'd bid it per sq foot. More money that way.
     
  10. YardPro

    YardPro LawnSite Gold Member
    Posts: 3,563

    i would also estimate qround 20 hours....

    we lay big rolls with the dingo... a helper and i can lay 1K yards in less than a day.
     