    Customer needs to irrigate an area that is on the other side of fresh pavement.

    Best route by far is direct line under pavement. Plan was to trench and put a sleeve in . Customer would take care of pavement after trenching and pipe install. Heavy trucks use the pavement. Boring is not an option.

    I have been told here that regular trenches like a Dingo need special teeth for pavement. Ditch Witch says they have a 50 hp model that will do the job. $700 for the rental. About 100' total to be trenched.

    Opines anyone?

    John
     
  2. greenmonster304

    greenmonster304 LawnSite Gold Member
    Posts: 3,074

    Why is boring not an option?
    Posted via Mobile Device
     
  3. jcom

    jcom LawnSite Senior Member
    Posts: 791

    The company here that can bore this area wants 2k to do the job. Too much for the customer. Looking for some way to trench and sleeve.

    We need to put pipe and cable inside a sleeve as the traffic would shred just pipe and cable alone. IMHO.

    John
     
  4. GreenI.A.

    GreenI.A. LawnSite Silver Member
    Posts: 2,132

    If your going to trench it, why not just cut out the section of pavement and remove it. Then just trench through the base and soil underneath?
     
  5. alldayrj

    alldayrj LawnSite Gold Member
    Posts: 3,767

    Use a cutoff saw with a diamond blade and dig by hand or a lesser trencher. 700 for a rental is crazy
    Posted via Mobile Device
     
  6. SRT8

    SRT8 LawnSite Bronze Member
    from CA
    Posts: 1,291

    Rent a walkbehind concrete cutting saw. It will give you clean lines unlike that trencher you are trying to rent. Then dig by hand and install your pipe. The clean lines from the concrete saw are going to make the patch of a pavement look a lot cleaner when you are done.
     
  7. Mdirrigation

    Mdirrigation LawnSite Silver Member
    Posts: 2,565

    2 grand is a good price to bore 100 feet under pavement . By the time you cut the pavement , trench or hand dig , rent a jumping jack to compact the dirt , and then they spend money to restore the pavement the cost will be the same if not more .

    If you are good rent a missile with 60 feet of hose , cut out a rectangle at the mid point and shoot each way , now you only have a small patch .
     
  8. greenmonster304

    greenmonster304 LawnSite Gold Member
    Posts: 3,074

    Hey MD how far have you ever shot with your missile?
    Posted via Mobile Device
     
  9. Mdirrigation

    Mdirrigation LawnSite Silver Member
    Posts: 2,565

    My longest shot was 55 feet , it was tight clay and mica soil . It was with a 2.5 millsile under a parking lot for an electrician running new wires to a light pole . $ 20.00 a foot
     
  10. jcom

    jcom LawnSite Senior Member
    Posts: 791

    We have the boring unit on our DW 255 so no missile available.

    Will check on a concrete cutting saw.

    Thanks all.

    John
     