    I'm pretty confident about my prices but this one job I'm bidding is larger than I'm use to.

    18,000sq. ft.
    4" topsoil @ 225yds.
    Hydroseed
    4 man crew will be on site
    2 days work pending on delivery of soil.

    Would like to what you would bid with cost of equip., labor, and your mark up. The homeowner is taking care of flowerbeds so all we have to do is bring in soil, rake final grade and, spray with Hydroseed. Also, are my caculations correct for the topsoil?
     
  2. mxrdrvr3

    mxrdrvr3 LawnSite Member
    Posts: 50

    sracthing head I come up with 22.5 yrds but I many be wrong
     
  3. diginahole

    diginahole LawnSite Member
    Posts: 249

    no, it is 225 yards, well 222.22 to be exact.
     
  4. rodfather

    rodfather LawnSite Fanatic
    Posts: 9,501

    You're going to use 225 yards of topsoil on just over 4/10ths of an acre? And at only 4" deep?
     
  5. Mykster

    Mykster LawnSite Senior Member
    Posts: 668

    That's why I asked if my caculations on the topsoil were correct. Too much? Too little?
     
  6. gslam88

    gslam88 LawnSite Member
    Posts: 146

    well let see


    225 yards about $4050 for topsoil cost plus markup = $4,500
    you can probably get this knocked down and getting someone to bring this in for less. Should be 13 trucks if trucking in its about $55 hour to truck


    4 man crew at @25/ hour $1,600

    are you spreading this by hard, or are you using a skid steer or loader of sorts?

    Depending on that added cost

    hydro not sure of charge as I do not do it currently.


    so far $6,100 plus additionals..
     
  7. Mykster

    Mykster LawnSite Senior Member
    Posts: 668

    skid steer.
     
  8. gslam88

    gslam88 LawnSite Member
    Posts: 146

    ok

    so then add $ 400 for skid steer and $400 for paying an opperator for 2 days at $25/ hour


    Is there any site prep work to be done by you or is the home owner doing it all


    Pete
     
  9. mxrdrvr3

    mxrdrvr3 LawnSite Member
    Posts: 50

    yeah 225 yards ....lol what the hell was I thinking with 22.5 DUH:D
     
  10. PAPS

    PAPS LawnSite Senior Member
    Posts: 404

    My bid for this job:

    1. (225) yards of topsoil installed ($50.00/yard at discount due to quantity)
    = $11,250.

    2. Hydro-seed = .10 per sq/ft.
    = $1800.00


    Total: $13,000 ~


    Duration: (1-1.5) days at (4-6) laborers and (2) Bobcats with operators.

    -I would run (2) tandem dumps delivering dirt and running the (2) Bobcats at the same time with the (4-6) laborers raking/grading the soil as we move it.
     