Production on pavers, in square feet

Discussion in 'Hardscaping' started by cleancutccl, Jun 22, 2009.

  1. cleancutccl

    cleancutccl LawnSite Senior Member
    Posts: 698

    Just wondering what some other companies paver production is per day 10 hour day. I'm just talking screeding sand and laying pavers, then if you know how many tons of base per day that would be a good comparison too. Thanks,

    Garrett
     
  2. Sunscaper

    Sunscaper LawnSite Senior Member
    Posts: 306

    600-800 square feet per man
     
  3. philboudreault

    philboudreault LawnSite Member
    Posts: 27

    no job is really the same old house ... new houses .....different stones....design and cuts all make a huge difference....but for a plain jane come in and install u should go with sunscaper's 600-800 feet .....but then a gain ...so many factors
     
  4. cleancutccl

    cleancutccl LawnSite Senior Member
    Posts: 698

    sunscaper, how many man crew are you talking?
     
  5. Sunscaper

    Sunscaper LawnSite Senior Member
    Posts: 306

    I run anywhere from 3-10 depending on the job. As philboudreault stated though this is a rough estimate on a straight run i.e. parking lots, or large driveways. Cuts are the death of productivity. Hope this helps you.
     