Sod installation time estimate to complete.

Discussion in 'Landscape Architecture and Design' started by mikestr, Apr 2, 2005.

  1. mikestr

    mikestr LawnSite Member
    from Toronto
    Posts: 87

    Just a quick questions.

    Pretty new to the game but, how long should it take 3 guys to do approx 2000sf of sod installation? Including prep, a 1-2" layer of additional soil for levelling and laying it down etc.. I may need to use a sod cutter to remove old patchy areas that exist as well.

    Thanks in advance.
     
  2. olderthandirt

    olderthandirt LawnSite Platinum Member
    from here
    Posts: 4,900

    After prep since I have no way of knowing what you have to do or the equipment you have available, it should take 3 guys only a few hrs to lay the sod if its been placed close to the area that needs it.
     
  3. AL Inc

    AL Inc LawnSite Bronze Member
    Posts: 1,218

    Yes, the prep work will take much longer than actually laying the sod.
     
  4. scraper69

    scraper69 LawnSite Senior Member
    from mi
    Posts: 477

    Plan on a good full day, (8-10) hours - Completed
     