1. Missed the live Ask the Expert event?
    Not to worry. Check out the archived thread of the Q&A with Ken Hutcheson, President of U.S. Lawns, and the LawnSite community on the Franchising Forum.

    Dismiss Notice

Time Estimate

Discussion in 'Landscape Maintenance' started by Forever Green Landscaping, Mar 7, 2012.

  1. Forever Green Landscaping

    Forever Green Landscaping LawnSite Member
    Posts: 138

    I can usually estimate on my own without having to ask on here but this is a little different.

    How long would it take 2 guys to dig a 4'x4'x4' hole for a catch basin from gutter and sump pump?
    I was hoping to use the labor to prevent running a machine across the lawn and tearing it up.
     
  2. Deererunner

    Deererunner LawnSite Senior Member
    from NJ
    Posts: 319

    Honestly, it is going to depend on the type of soil your trying to dig through. I actually just did the same thing for a customer last month, took me about an hour by myself but had ideal soil conditions to dig by hand. If you have clay or rookie soil, going to take a lot longer. Sandy conditions could also increase time due to may have small cave ins.

    Hope this helps...
     
  3. KeystoneLawn&Landscaping

    KeystoneLawn&Landscaping LawnSite Senior Member
    Posts: 774

    I use a sub with a mini that has pads and only excerts 70lbs per square inch....just leaves a little indentation...worth the cost...hand digging sucks!
     

Share This Page