1. JTS Landscaping lawn

    JTS Landscaping lawn LawnSite Senior Member
    Posts: 378

    im a little slow with math today i have a sod install im bidding on its 600sq. ft. how many yards top soil going to need was thinking 16 but some reason doesnt seem right.
     
  2. Isobel

    Isobel LawnSite Senior Member
    Posts: 548

    that give you a little less than 9" of toil soil over the 600 square feet.
     
  3. JTS Landscaping lawn

    JTS Landscaping lawn LawnSite Senior Member
    Posts: 378

    lol yeh thats little to much its only got to be like 3-4"
     
  4. Jb3NH

    Jb3NH LawnSite Member
    Posts: 197

    600sq/ft.

    • 2.5" 4.6 yards
    • 3" 5.5 yards
    • 3.5" 6.5 yards
    • 4" 7.5 yards
    • 4.5" 8 and a third yards
    • 5" 9 and a third yards
    • 5.5" 10 and a quarter yard
    • 6" 11 and a quarter yard
    • 6.5" 12 yards
    • 7" 13 yards

    These numbers do not account for compaction, I try and use 20%
     
  5. JTS Landscaping lawn

    JTS Landscaping lawn LawnSite Senior Member
    Posts: 378

    hey thanks so much for your help. this math stuff isnt always for me lol.
     