Gravel fill behind SRW.

Discussion in 'Hardscaping' started by tamo, Jan 24, 2011.

  1. tamo

    tamo LawnSite Member
    Messages: 213

    I've seen people use both 3/4 minus and clean gravel without fines as fill behind retaining walls.

    What is the best material to use? I'd think the clean gravel for better drainage, but I've seen and heard othewise.

    Thanks.
     
  2. STL Ponds and Waterfalls

    STL Ponds and Waterfalls LawnSite Bronze Member
    Messages: 1,174

    We alway's use clean.
     
  3. Bru75

    Bru75 LawnSite Senior Member
    Messages: 582

    Definitely clean, you don't want it to hold water.
     
  4. BrendonTW

    BrendonTW LawnSite Senior Member
    Male, from Oklahoma City
    Messages: 613

    Clean. The NDS representative came and spoke in a class I was in a few weeks ago and said to use river rock due to the much bigger voids, cleanliness, and resistance to absorb water. I think that's ideal, but probably not economical.
     
  5. NewHorizon's Land

    NewHorizon's Land LawnSite Senior Member
    Messages: 689

    Your retaining walls should be engineered. The engineer will tell you what material to use. Clean is always the best bet.
     
  6. jonesy5149

    jonesy5149 LawnSite Senior Member
    from Maine
    Messages: 259

    Well we do 3/4 washed crushed rock and with 150 fabric and then 500x on the top and 6'' to 12'' of gravel. compacted about 75% proctor then mulch or loam.
     
  7. PatriotLandscape

    PatriotLandscape LawnSite Bronze Member
    from MA
    Messages: 1,209

    75% proctor? How did you test that?

    3/4 dropped in a hole is already 90% without running the compactor on it.
    Posted via Mobile Device
     
  8. DVS Hardscaper

    DVS Hardscaper LawnSite Fanatic
    Messages: 6,543


    Patl-scape, about a month ago I typed the same thing and some guru here told me i wrong!


    ,
     
  9. jonesy5149

    jonesy5149 LawnSite Senior Member
    from Maine
    Messages: 259

    the 3/4 rock is 90% but the 6 to 8 inchs of grave i rap at the top befor the loam or mulch i just get the proctor to 70% about 4 passes with the 7500 bowmag. we test with a rod and a .5 lbs of weight and it will sink about 1/4 passed the line. we had are sand and gravel tested last year to get a device to measure it. the sand pit we bought has lots of great products in it.
     
  10. jonesy5149

    jonesy5149 LawnSite Senior Member
    from Maine
    Messages: 259

    How are you guys doing for the compaction rate?? Tool or guess ??
     